Commercial construction loan requirements checklist

A commercial construction loan requires an experienced sponsor with liquidity to cover overruns, a controlled and entitled site, permit-ready plans, a detailed budget with contingency, a signed contract with a qualified general contractor, cash or land equity that funds ahead of the loan, a funded interest reserve, and a credible takeout. Lenders also order an as-completed appraisal, an environmental report, and an independent plan and cost review before closing.

Updated

Worked examples
Hypothetical, labeled in the text
Loan size we arrange
$1M to $100M
Key facts
DetailExplanation
SponsorCompleted projects of similar type and size, plus liquidity for cost overruns
SiteOwned or under contract, zoned for the use, with entitlements approved
CostHard and soft cost budget with contingency, tied to a signed construction contract
EquityUsually funded before the first loan draw, in cash or approved land value
GuarantiesCompletion, carry, and often repayment or carve-out guaranties
ExitA permanent loan or sale supported by stabilized income

How to use this checklist

This page lists what construction lenders ask for. For the reasoning behind each item, such as how lenders treat land basis, contingency, and takeout sizing, read how commercial construction lenders underwrite. Requirements vary by lender and property type, so treat each table as the baseline a first submission should meet.

What are the sponsor requirements for a construction loan?

Construction lenders underwrite the people as closely as the project, because the sponsor and guarantors stand behind a completion guarantee and fund any shortfall.

Sponsor and guarantor checklist
RequirementWhat lenders look for
Development track recordCompleted projects of the same property type, similar scale, and similar construction method, with budget and schedule results
Development teamA general contractor, architect, engineer, and property manager with relevant experience where the sponsor lacks it
LiquidityUnencumbered cash after the equity is funded, enough to cover overruns and carry during delays
Net worthBalance sheet strength that supports the guaranties, net of obligations on other projects
Contingent liabilitiesA schedule of every guaranty and loan the sponsor already carries, with maturities
Credit and backgroundClean credit and background reports on principals, with explanations for any past events
GuarantiesWillingness to sign a completion guaranty, a carry guaranty, and any repayment or carve-out guaranty the lender requires

What site and entitlement documents do lenders require?

Site checklist
DocumentWhat lenders look for
Deed or purchase contractOwnership or a contract that closes with the loan, plus the settlement statement showing land basis
Zoning verificationThe planned use and density permitted by right or by an approval already granted
Entitlements and conditions of approvalFinal approvals, conditions that add cost, and any appeal periods still open
Building permitsIssued permits or a clear path to issuance before the first draw
Utility will-serve lettersWater, sewer, power, and gas capacity committed to the site
ALTA surveyBoundaries, easements, access, and flood zone
Phase I environmental reportNo unresolved recognized environmental conditions
Geotechnical reportSoil conditions that match the foundation design and budget

What budget and contract documents are required?

Construction lenders fund against a budget, so the budget and the contract have to agree line by line. Many lenders prefer a guaranteed maximum price contract because it moves part of the cost risk to the contractor.

Budget and contract checklist
DocumentWhat lenders look for
Sources and usesEvery cost and every source of funds, balanced and matching the budget
Hard cost budgetLine items supported by bids or a contractor estimate
Soft cost budgetDesign, permits, impact fees, legal, insurance, taxes, marketing, and financing costs
ContingencyHard and soft cost contingency sized to the stage of design and bidding
Construction contractContract type, price, schedule, allowances, exclusions, retainage, and change-order process
General contractor packageLicense, financial statements, bonding capacity, insurance, and references
Plans and specificationsPermit-ready drawings that match the contract scope
Construction scheduleMilestones from site work through certificate of occupancy
Architect and engineer agreementsScope, fees, and consent to assignment to the lender

How much equity does a construction loan require?

Construction loans are sized mainly by loan-to-cost, checked against the as-completed or as-stabilized value. The borrower funds the difference between total project cost and the loan, and most lenders require that equity to go in before the first loan dollar.

In this hypothetical example, total project cost is $20,000,000 and the lender advances 65% of cost. The loan is $13,000,000 and the sponsor must fund $7,000,000 of equity, or 35% of cost.

Hypothetical construction capitalization
ItemAmount
Total project cost$20,000,000
Loan at 65% of cost$13,000,000
Required sponsor equity$7,000,000
Equity share of cost35%

What equity documentation will the lender ask for?

  • Bank or brokerage statements showing the cash equity
  • Settlement statement and appraisal support for any land contributed as equity
  • Paid invoices for predevelopment costs claimed as equity
  • Investor subscription documents or capital call rights for outside equity
  • Terms of any subordinate debt or preferred equity in the capital stack

Which third-party reports does the lender order?

The borrower pays for these reports, but the lender engages the providers and relies on the results.

  • Appraisal with as-is land value and as-completed or as-stabilized value
  • Plan and cost review by an independent construction consultant
  • Phase I environmental site assessment, plus a Phase II if the Phase I recommends one
  • Title commitment and ALTA survey
  • Zoning report where the lender does not rely on the municipality's letter
  • Market study for lease-up or sale assumptions on larger projects

What must be in place before closing and the first draw?

  • Builder's risk, general liability, and contractor insurance naming the lender
  • Payment and performance bonds or other contractor security if required
  • Contractor, architect, and engineer consents to assignment
  • Borrower equity funded and verified
  • Interest reserve and any other reserves funded from the budget
  • Building permits issued
  • An agreed draw process with the inspecting consultant, lien waiver requirements, and retainage terms

What exit do construction lenders require?

The lender wants to see how the loan gets repaid when construction ends. For a hold, that means stabilized net operating income that would support a permanent loan at the construction loan balance. For a sale, it means market evidence for the sale price and time to sell. Pre-leasing, a signed lease with a creditworthy tenant, or a forward purchase commitment strengthens the exit, and some lenders require one of them for speculative projects.

Submitting a construction request

A request does not need every item above to start a lender conversation, but it needs the sources and uses, budget, site status, entitlement status, and sponsor track record. Capital Partners arranges commercial construction loans within its $1M to $100M range and reviews each project against the lenders active for that property type and market. Submit the project for a principal's review to learn which items lenders will question first.

Common questions

What do you need to get a commercial construction loan?

You need a controlled and entitled site, permit-ready plans, a detailed budget with contingency, a signed contract with a qualified general contractor, equity to fund ahead of the loan, and a sponsor with relevant experience and liquidity. Lenders also require guaranties and a clear exit through a permanent loan or sale.

Can land count as equity on a construction loan?

Often, yes. Lenders credit owned land toward the equity requirement, but each lender decides whether to credit the original cost or the appraised value. Recently acquired land usually receives credit closer to its purchase price.

Do I need building permits before closing a construction loan?

Most lenders require issued permits before closing or before the first construction draw. Some will close with permits pending when the only remaining steps are administrative, and hold loan funds until the permits are issued.

Do construction lenders require a general contractor?

Almost always. Lenders want a licensed, insured, and financially capable general contractor under a signed contract. A sponsor that acts as its own contractor needs a track record doing so, and the lender may require extra guaranties or bonding.

What guaranties does a construction loan require?

A completion guaranty is standard, and many lenders also require a carry guaranty covering interest, taxes, and insurance until stabilization. Banks often add a full or partial repayment guaranty, while some non-bank lenders limit recourse to carve-outs.

Send this deal to a principal

Share the basics now. A principal responds within 1 business day, and you can send the full package after the first conversation.

Have an offering memorandum? Use the full submission form to attach it.